Site Activity – Demolition and Enabling Contract

2017

    • Hoarding erected end Jan
    • Planning compliance submission
    • Services installation starts

    • Demolish Weigh Room (17d)
    • Start demo. of grand-stand
    • Start Demo. Of Queens Room

    • West Stand (24 days) gone
    • Site prepared progressively Following demolition

    • Temp. Facilities erected

  • Truncated Racing Season

    • Temp. Facilities Live
    • East Stand (26days) Gone
    • Queens Room demo done

  • Truncated Racing Season

    • Queens Room foundations and re-build starts

  • Truncated Racing Season

    • Enabling works complete
    • Services installation completes
    • (Main Con. Awarded end July)

  • Truncated Racing Season

    • Main Contract Starts on Site

  • Truncated Racing Season

    • Queens Room Complete

Site Activity – Stableyard

2017

    • Hoarding erected end Jan
    • Start Blocks A-F refurb
    • Start new Machinery Yard at rear

    • Re-furb. ongoing

    • Re-furb. ongoing

    • Blocks A-F Complete before start of season
    • Ground works in machinery yard

  • Truncated Racing Season

    • Complete new machinery yard buildings

  • Truncated Racing Season

    • Minor works only

  • Truncated Racing Season

    • Minor works only

  • Truncated Racing Season

    • Minor works only

    • Minor works only

    Truncated Racing Season

    • Commence new stable yard
    • Commence drainage works
    • Dismantle existing ‘shed’

    • Re-erect shed

Site Activity – Stableyard

2018

    • New stable yard complete
    • New wash bays

  • Stable Yard Target completion

Projected Program

08/02/2017

SOS = Start On Site
ITT = Invitation to Tender
SAQ = Suitability Assessment Questionnaire
MC = Main Contractor
MCSub = Subcontractor to Main Contractor
WWT = Waste Water Treatment Works
TF = Temporary Facilities
SY = Stable Yard

    • Planning Granted
    • VE Concluded

    • ITT Demo + Enabling Works Issued
    • ITT Stable Yard Issued

    • MC SAQ + 6 SUBS
    • Temp Fac. Tender competition issued

    • TF -Award Contract end of Nov

    • LOI for Demo + Enabling + Stable Yard
    • Appoint Temp. Fac. provider

    • Demolition + StableYard Start On Site
    • MC + MCSub ITT Issued

    • ITT WWT

    • MC Tender return
    • MC Selection

    • Temp. Facilities erected
    • Return of Tenders for WWT

    • TF Live
    • 6 MC Sub Tender Return

    Truncated Racing Season

    • Demolition + Enabling completion target
    • WWT SOS

    Truncated Racing Season

    • Enabling + Demolition Completes
    • Main Con. Awarded end July

    Truncated Racing Season

    • Main Contract Starts on Site

    Truncated Racing Season

  • Truncated Racing Season

    • Temp. facilities removed
    • WWT completion target

    • Construct Parade Rings
    • Construct Entrance Wing

    • Complete Queens Room

    • Stable Yard Completes

    • Temp. Facilities Erected

    • TF Live

    Truncated Racing Season

  • Truncated Racing Season

  • Truncated Racing Season

  • Truncated Racing Season

  • Truncated Racing Season

    • Temp. facilities removed

    • Main Contract  Completes